Contract execution
Contract execution is the process of signing an agreed contract, after which its terms become binding on the parties to the contract.
Contract engrossment is the process of preparing the final agreed form of contract and its schedules and appendices so that it can be executed. Engrossed contracts are then either executed under seal (signed by the parties, witnessed and most importantly made clear that they are executed as a deed) or under hand (a 'simple contract' that is just signed by the parties).
Simple contracts and contracts under seal have different limitation periods. An action founded on simple contract cannot be brought after six years from the date on which the cause of the action accrued. The limitation period for a contract under seal is 12 years. See Contracts under seal v under hand for more information.
Generally, two engrossed contracts will be prepared for execution, one for the client and one for the supplier. Alternatively, one party might retain the executed contract, with certified copies being issued to the other party, this can avoid potential errors in preparing two contracts for execution.
It is very important to ensure all details entered into the contract are correct before signing. It is surprisingly common for example for the wrong company to be named in the contract, and whilst the courts may see this as a clerical error that should be corrected, this should not be relied upon, particularly in the case of insolvency, and court proceedings in themselves are likely to be costly and time consuming.
See:
- Derek Hodd Limited v Climate Change Capital Limited.
- Genesis Housing Association Limited v Liberty Syndicate Management Limited.
- Westshield Civil Engineering Ltd and Westshield Ltd v Buckingham Group Contracting Ltd.
It is also relatively common for contract execution to be delayed until well after the actual works described in the contract have been started. Clearly this is not advisable.
Letters of intent are sometimes used as interim arrangements to mobilise a supplier prior to a formal contract being executed, but they should never be seen as an alternative to a full contract and should place a limit on expenditure and liability prior to the contract being put in place. See letter of intent for more information.
[edit] Related articles on Designing Buildings
- Articles of agreement.
- Conformed contract.
- Construction contract.
- Construing a contract.
- Contract award.
- Contract conditions.
- Contract documents.
- Contract engrossment
- Contracts under seal v under hand.
- Derek Hodd Limited v Climate Change Capital Limited.
- ESignatures.
- Essentials of a contract.
- Form of tender.
- Genesis Housing Association Limited v Liberty Syndicate Management Limited.
- Glossary of property law terms.
- Letter of intent.
- Privity of contract.
- Westshield Civil Engineering Ltd and Westshield Ltd v Buckingham Group Contracting Ltd.
Featured articles and news
Futurebuild and UK Construction Week London Unite
Creating the UK’s Built Environment Super Event and over 25 other key partnerships.
Welsh and Scottish 2026 elections
Manifestos for the built environment for upcoming same May day elections.
Advancing BIM education with a competency framework
“We don’t need people who can just draw in 3D. We need people who can think in data.”
Guidance notes to prepare for April ERA changes
From the Electrical Contractors' Association Employee Relations team.
Significant changes to be seen from the new ERA in 2026 and 2027, starting on 6 April 2026.
First aid in the modern workplace with St John Ambulance.
Ireland's National Residential Retrofit Plan
Staged initiatives introduced step by step.
Solar panels, pitched roofs and risk of fire spread
60% increase in solar panel fires prompts tests and installation warnings.
Modernising heat networks with Heat interface unit
Why HIUs hold the key to efficiency upgrades.
Reflecting on the work of the CIOB Academy
Looking back on 2025 and where it's going next.
Procurement in construction: Knowledge hub
Brief, overview, key articles and over 1000 more covering procurement.
Sir John Betjeman’s love of Victorian church architecture.
Exchange for Change for UK deposit return scheme
The UK Deposit Management Organisation established to deliver Deposit Return Scheme unveils trading name.
A guide to integrating heat pumps
As the Future Homes Standard approaches Future Homes Hub publishes hints and tips for Architects and Architectural Technologists.
BSR as a standalone body; statements, key roles, context
Statements from key figures in key and changing roles.
Resident engagement as the key to successful retrofits
Retrofit is about people, not just buildings, from early starts to beyond handover.